| Meeting
with Focus Groups |
As
soon as possible after March 24 for orientation and to talk
about how to communicate ESLRs schoolwide and to consider
them in relation to timelines.
|
| HG:
Meet to create assessment tools for ESLRs |
Deadline:
April 28
Assessments
should be in place and ready for use by key teachers on
May 5 - the first day of our
summer session.
All
teachers should know how to use the assessments or develop
their own for use by September 2
- the first day of our Fall session.
|
| FG:
Determine data from staff/community needed to answer criteria
questions |
This
activity will be done while preparing ESLR assessments
March
25 to April 7
|
April
7 to
April 28
|
May
5 to
May 19
|
May
27 to
June 9
|
| FG:
Gather data from staff/community needed to answer criteria questions |
| FG:
Determine student data needed to answer criteria questions |
April
7 to April 28
|
April
28 to
May 19
|
May
19 to
June 9
|
June
9 to
July 1
|
| HG:
Develop tools to gather data |
| HG:
Gather student data needed to answer criteria questions |
| FG:
Synthesize data gathered from HGs. Ask HGs to collect more and
different kinds of data if necessary. |
Deadline:
July 8, 2003
|
| FG:
Determine strengths and growth needs |
|
|
|
|
|